The Old Milton Highway Addition expands the existing home with a new 25' × 25' garage, laundry room, and additional living space. The project combines new construction and updated exterior finishes to create a seamless extension of the original home.
Update October 14, 2026
Progress continues at our Old Milton Highway garage project. The Therma-Tru exterior doors and windows have now been installed, bringing the building another step closer to completion.
With these installations complete, the structure is ready for siding. This next phase will bring the exterior appearance together as we continue moving toward the finishing stages of construction.
Update September 7, 2026
Mechanical, electrical, and plumbing rough-ins are now complete at the Old Milton Garage project. With these systems in place, the interior is ready for the next phase of work.
Insulation is up next, preparing the walls and ceilings before interior finishes begin.
Update July 1, 2026
Roof trusses are being installed on the Old Milton Highway Addition, bringing the new roof structure together over the garage and expanded living spaces. With the trusses in place, the overall shape of the addition is becoming fully defined.
Next, roof sheathing and roofing will begin as we work toward getting the addition dried in.
Update June 19, 2026
Exterior wall framing is complete on the Old Milton Highway Addition, bringing the new garage and expanded living spaces above the foundation. With the walls standing and the shape of the addition established, the project is ready to move into roof framing.
Next, the roof structure will begin tying the new addition into the existing home.
Update May 22, 2026
The foundation is poured and framing of the new floor system is underway at the Old Milton Highway Addition. With the foundation complete, the addition is beginning to transition from concrete work into the structural framing phase.
Next, the floor system will be completed and wall framing will begin.
Update May 11, 2026
Excavation is complete for the Old Milton Highway Addition, and footing installation is underway. With the site prepared and the new footprint established, work is moving into the foundation phase that will support the garage and expanded living spaces.
Next, the footings will be poured and foundation construction will continue.